There
were many variations on this basic theme of balanced double
acting
incline, some of these were:
| Uphaulage | single tracked and powered, used for hauling up from a pit and extensively underground. |
| Table | where the trucks were pushed onto a horizontal table, often these table inclines were of a wider track gauge. |
| Water balance | using the weight of a tank of water as a counterbalance. |
| Chain incline | using wire or chain instead of rails, used to access deep pits. |
| Blondin or aerial ropeway | A wire strung across a pit between two towers, wagons lowered or raised from below |
At
the zenith of the industry there were over 500 gravity balanced inclines
in operation.
The
last was taken out of use in 1976 at Maenofferen Quarry, Blaenau Ffestiniog.
A
gravity incline drumhouse
The
drumhouse shown above worked the very last gravity incline to operate in
North Wales. Wagons of roofing slates were worked, or crewled, from
Maenofferen Quarry in Blaenau Ffestiniog down this incline to a lower level
for onward transport by road vehicle. The incline closed in 1976
but is still reasonably intact except for the roof. On the drum are
the two ropes - one wound over and the other under for the two tramway
tracks. On the left of the drum is the strap brake which is worked
by the long brake handle. Being an incline brakesman was a highly
skilled and responsible job.
Rhiwbach No.3 incline,
near Blaenau Ffestiniog.
A
view of Rhiwbach No. 3 incline. A classic balanced double acting
incline. At the top may be seen the supporting walls of the now collapsed
drumhead around which the two ropes were wound. Inclines of this
length only became practicable after the invention of steel wire reinforced
ropes. A similar length using hessian ropes would have required two
or three separate inclines.
This
incline was used to haul slate from underground. Power was provided by
a nearby steam engine.
The principle of table inclines was that the narrow gauge wagons were carried on a horizontal platform. The track on these inclines was of a wider gauge and the platform allowed up to 4 wagons to be carried at once. In this photograph of the restored Dinorwic table incline at the National Slate Museum in Llanberis, the table is seen in the midway position. The table is now electrically powered but originally was worked by gravity. Below can be seen the arrangement of the rails on top of the table.
The
preserved Water Balance at Penrhyn Quarry, Bethesda. The two movable
platforms of the incline had tanks for water beneath. An empty wagon
with a full tank of water would haul up a loaded wagon with its water tank
empty. The raised tank on the right contained water which was used to supply
the tanks under the platforms. Penrhyn at one time had eight of these
balances and this one was named Sebastopol, as it was built during the
Crimean War. Photograph obtained with the permission of Alfred Macalpine
Slate Ltd.
As
Aberllefenni Quarry near Corris developed over the years it began to run
out of tipping space for waste rock. The solution was to tip higher
up on the other side of the valley. To raise the waste rock several
water balances, like this one, were constructed. The tank is
mounted on a wheeled chassis and when a wagon of waste rock needed to be
raised the tank was filled with water, the tank was then lowered down so
raising the other wagon. At the bottom the water was let out and
the wagon was returned to the top.
Aerial ropeways or Blondins were widely used in the industry and had the advantage over fixed inclines of being portable. They were particularly used in the Nantlle area to access the deep pit workings. The Blondin consisted of a number of cables strung across the working area. When the wagon was attached, the cable was hauled out until it was above the working area, the wagon was then lowered to the bottom of the quarry. The last working examples were in use until 1979 at Pen yr Orsedd Quarry, Nantlle. The top photo is taken in Dinorwic while the bottom shows a Pen yr Orsedd cradle. There are noticeable differences between the two types.
This
simple system enabled slate quarried at a higher level to be lowered to
a dressing shed
lower
down. At the top is the wheel for the wire rope while at the bottom
is another wheel on which
the
strap brake acted. The slate blocks would travel on cradles suspended
from the wire rope.
Prince of Wales
Quarry
This
view shows how the long central gravity incline in the background could
serve several different levels of a quarry. The drumhouse in the
foreground let wagons down to the dressing area.
This
is the collapsed tower of an aerial ropeway in Dyffryn Nantlle.